The next thing to look at are the batteries:

Voltage readings from the servo battery pack

There are a few things notable about this graph. First off, the servo voltage is a bit high. Apparently the CC UBEC was set to 5.6V? It should be set to 5.3V or so I think. We want plenty of safety margin below the 5.7V limit for the servo rail being a backup power supply for the FMU.

We also see some voltage spikes on the servo rail. I think we should install a reverse biased zener diode on the servo rail to clip those. That will ensure that if primary FMU power fails the servo rail is a good backup. See here for details.

The next thing that is noticeable is the POWR.Vcc is quite low. That is normally steady at 5V. Seeing the match to the CURR.Volt value, it looks like this is just diode drop in the power brick, combined with voltage drop in the main FMU power supply with the cold temperatures.

The Vcc stayed well above the level the board can handle, so it is OK, but it sure would be nice to fix the servo rail as a backup supply in case it drops any more. That battery pack dropped to 5.1V (see below), which is quite a drop.

Servo rail and battery voltages during the test flight

In summary, then, we've got a few issues, but nothing insurmountable. Just when we hoped we'd done the final test flight, it looks like a further jaunt is on the cards, with the following adjustments:

  1. Enhanced battery monitoring for both packs
  2. Move pitot to be in clear air
  3. Zero airspeed offset before launch
  4. Change CC UBEC voltage down to 5.3V
  5. Add zener clipping diode

And while we're at it, Tridge has suggested we give the Vulture 2's RFD 900u Radio Modem a run for its money.

the RFD 900 rig

We recently installed this long-range kit, which replaces the standard 3D Robotics radio. With its big brother the RFD 900 (at top, above) on the ground, we'll be able to monitor the aircraft live via the APM Mission Planner.

Of course, that opens the possibility of Tridge ultimately monitoring and controlling the spaceplane via VPN from the comfort of his PC in Australia, which is a very provocative possibility indeed.

We'll bring you details of quite how that hook-up works in practice when Tridge and Edge have mulled the practicalities. ®

Bootnotes

*We've hitherto rather rudely failed to mention Tridge and fellow CanberraUAV team members' triumph in the 2014 UAV Outback Challenge.

The simple premise of the challenge is to detect a dummy dubbed "Outback Joe" and drop a water bottle as close to him as possible. As you might imagine, there's some serious work involved in making that happen, so we invite readers to raise the traditional glass to CanberraUAV for a truly impressive feat.

**Not vanity on my part, I assure you, but rather a piece of unprompted backronym tomfoolery by Edge, very much in the spirit of LOHAN.


The Low Orbit Helium Assisted Navigator, sponsored by...

  • EXASOL logo
  • Pulse_Eight
  • SecQuest logo
  • Lucidica logo
  • NXT logo

...and with the invaluable support of...

  • Edge Research Laboratory logo
  • Space Graphic Solutions logo
  • 3D Robotics logo
  • 3T RPD logo
  • University of Southampton logo
  • Applied Vacuum Engineering logo
  • Escher Technologies
  • Flashpoint Fireworks logo
  • HAB Supplies logo
  • Rock 7 logo
  • Random Engineering logo

More from the lovely LOHAN:

  • You can find full LOHAN coverage right here.
  • If you're new to LOHAN, seek out our mission summary for enlightenment.
  • There are photos our our magnificent Vulture 2 spaceplane here, and detailed structural plans here.
  • For your further viewing pleasure, we have all our photographic material stored on Flickr.
  • Our LOHAN and Paper Aircraft Released Into Space (PARIS) videos live on YouTube.
  • We sometimes indulge in light consensual tweeting, as you can see here.

More about

More about

More about

TIP US OFF

Send us news


Other stories you might like