Call it climate or call it unusual weather, but last week's five-day heat wave in the Australian city of Melbourne got the sweat running at one of the country's major supercomputing facilities, the Victorian Life Science Computation Initiative (VLSCI).

The problem for sysadmins at VLSCI was simple: with temperatures remaining above 40°C for four days in a row, Melbourne's water got too hot, exceeding the intake specification for the facility's cooling system.

First to go was AVOCA, the 838.86 teraFLOPS Blue Gene/Q system that went live in 2012. On January 14, as the Melbourne City temperature approached 43°C, the VLCSI sys admins stated that “the water inlet temperatures have exceeded the safe limit for keeping AVOCA operational”.

Ten minutes later, the smaller MERRI and BARCOO (both IBM iDataplex x86 systems) also fell at risk of a sudden shutdown, and to cope, administrators stopped scheduling new jobs. So it remained overnight.

While the smaller supers were brought back online at 10 am on January 15, the near-42°C temperatures still kept AVOCA offline. With more work on January 16 – and in spite of the mercury getting close to 44°C, a single 8,192-core midplane of the machine was fired up.

And that's how things stayed through most of last Friday, which replicated Thursday's peak. A second midplane was fired up at 3pm. The machine was finally brought back into service after 5pm, after a cool change arrived.

The facility is now assessing modifications to the cooling system to help it cope with future extreme heatwaves.

The Bureau of Meteorology's heatwave forecast

Extreme weather has prompted Australia's Bureau of Meteorology to launch a pilot heatwave forecast service.

Meanwhile in the outside world, the heatwave was reportedly responsible for hundreds of cardiac arrests, according to Ambulance Victoria (one call every six minutes at the peak), and five hundred calls for heat exhaustion. It's not yet known how many deaths occurred as a result of the extreme weather.

A heatwave of last week's magnitude has not been recorded for decades in Australia, leading some to label the event a result of anthropogenic climate change. That claim's of course not been proven. But like most other data centre operators, Australia's seek to use low-energy cooling options whenever possible. When even the water supply can't deliver cold comfort, hotter days become a real problem for Reg readers, no matter the source of the heat. ®

Beginner's guide to SSL certificates

More from The Register

next story
Ellison: Sparc M7 is Oracle's most important silicon EVER
'Acceleration engines' key to performance, security, Larry says
Oracle SHELLSHOCKER - data titan lists unpatchables
Database kingpin lists 32 products that can't be patched (yet) as GNU fixes second vuln
Lenovo to finish $2.1bn IBM x86 server gobble in October
A lighter snack than expected – but what's a few $100m between friends, eh?
Ello? ello? ello?: Facebook challenger in DDoS KNOCKOUT
Gets back up again after half an hour though
Hey, what's a STORAGE company doing working on Internet-of-Cars?
Boo - it's not a terabyte car, it's just predictive maintenance and that
prev story

Whitepapers

Forging a new future with identity relationship management
Learn about ForgeRock's next generation IRM platform and how it is designed to empower CEOS's and enterprises to engage with consumers.
Storage capacity and performance optimization at Mizuno USA
Mizuno USA turn to Tegile storage technology to solve both their SAN and backup issues.
The next step in data security
With recent increased privacy concerns and computers becoming more powerful, the chance of hackers being able to crack smaller-sized RSA keys increases.
Security for virtualized datacentres
Legacy security solutions are inefficient due to the architectural differences between physical and virtual environments.
A strategic approach to identity relationship management
ForgeRock commissioned Forrester to evaluate companies’ IAM practices and requirements when it comes to customer-facing scenarios versus employee-facing ones.