Feeds

IBM committed 'ethical transgressions' to win botched project

Big Blue bid way too low, but Gov incompetence was main reason for $1bn blowout

  • alert
  • submit to reddit

Providing a secure and efficient Helpdesk

IBM has found to have acted unethically during a bid to win work developing a new payroll application for the Australian state of Queensland's Department of Health, but has not been held directly or solely responsible for the $AUD1bn blowout in costs on the project.

IBM's been under the microscope for its role in this project because it started life in 2007 as a $6m job. That became $27m and has now reached over a billion dollars, because the application is a dud: staff have been overpaid, underpaid, forced to repay money and sometimes not paid at all. With the health sector having a colossal and unionised workforce, those stories and the blowouts became political dynamite. That the only way to get the application working was to throw people at it – as of May 2012 1,010 people worked with the app and handled 92,000 forms a fortnight – meant the system had increased costs instead of producing savings.

Worst of all, despite the mess Queensland's government decided not to pursue IBM for damages, a scandal that meant when a new government formed an inquiry into the matter was a fine idea from both governance and political perspectives.

That inquiry's final report (PDF) emerged today and is not pretty reading for IBM or the State of Queensland.

Let's start with IBM, which as keen readers may recall found itself under investigation thanks to one Michael Burns, a former senior IBM executive who found himself consulting on the project to the Queensland government. Burns agreed with a policy to implement a prime contractor for the project and encouraged IBM to bid.

The report is not kind to Burns (referred to as 'Mr Burns' throughout), who the report says “entertained a distinct partiality for IBM and, indeed, displayed a bias in its favour”. That bias saw Burns adjust assessment criteria to favour IBM's bid.

IBM Global's s commercial and public sector, Lochlan James Bloomfield, also comes off badly, with the report saying he must have known that Burns “was behaving extraordinarily for a man charged with the responsibility of investigating a very substantial government IT program and guiding the procurement process for a contractor to take it over.” The report suggests Bloomfield's “emails to his superiors indicate that he understood that a valuable business opportunity was being offered to IBM which it should do its utmost to exploit. He cannot have thought the same favouritism was extended to his competitors.”

Bloomfield's competitors were Logica and Accenture, both of which were familiar with the Department and its operations, experience that made them well-placed to do the payroll job. But Burns encouraged IBM to bid too, and at some point IBMers also found themselves able to access information about their rivals' bids. There's a suggestion they used the information gleaned from those documents to underbid the pair.

IBM's lower price was the main factor in it winning the deal, but the report says “evidence gives rise to a suspicion that IBM offered a price to win the tender which did not genuinely express its estimation of the true costs involved. I cannot make a definitive finding to that effect but the evidence suggests that is a distinct possibility.”

The report is very clear that none of this activity was corrupt. Indeed, Burns' motives remain obscure as there's no evidence he stood to profit from supporting IBM.

What's crystal clear is that Queensland's procurement and project management processes were hopeless. The report finds that just one person with governance responsibility for the project raised objections to the odd procurement process and that those objections weren't acted upon. The State also offered a terrible brief for the project. Here's how Commissioner Richard N Chesterman describes it's work:

“The State did not adequately communicate to IBM the business requirements for the workforce of Queensland Health which would permit IBM to design a payroll system which accommodated the number and complexity of pay rules. IBM did not actively elicit information about those requirements which would have allowed it to design such a system. The result was ongoing disputes about scope which resulted in changes to the contract, increases in price, and delays to the implementation date.”

The project didn't go well, with partial releases proving inadequate, in part because software was taken live even though it was known to be unready.

Things went predictably badly and by 2010, Queensland wanted to be shot of IBM and received advice it could terminate Big Blue's contract and start lobbing flaming sueballs in its direction.

But the State decided not to do so and instead settled with the company “driven by assumptions that without IBM’s presence there was a substantial risk that the payroll system would fail utterly and that if the State insisted upon its contractual right to terminate, IBM would disregard its disengagement obligations and refuse to assist with the remediation and/or improvement of the system.”

The report says one of the State's negotiators were “timid”, capitulated during negotiations with IBM, and should instead have gone in hard because the State stood to gain tens of millions of dollars in damages.

Commissioner Chesterman makes many recommendations on how Queensland can improve its procurement practices to avoid such messes in future. He's also critical of the concept of shared services, saying this project's failure “may be the most spectacular example of all the unsuccessful attempts to impose a uniform solution on a highly complicated and individualised agency.”

Chesterman also says IBM should never have won the work, due to “ethical transgressions of its employees arising out of the use of Accenture’s information”, lack of scrutiny of its proposed price and because “Mr Burns’ intervention in the evaluation process distorted and seriously flawed the selection of the Prime Contractor”.

He concludes that “The replacement of the Queensland Health payroll system must take a place in the front rank of failures in public administration in this country. It may be the worst.”

The Reg is aware of none to match it in Australia, and few that paint a major global vendor in such a poor light. ®

Reducing the cost and complexity of web vulnerability management

More from The Register

next story
Phones 4u slips into administration after EE cuts ties with Brit mobe retailer
More than 5,500 jobs could be axed if rescue mission fails
JINGS! Microsoft Bing called Scots indyref RIGHT!
Redmond sporran metrics get one in the ten ring
Driving with an Apple Watch could land you with a £100 FINE
Bad news for tech-addicted fanbois behind the wheel
Murdoch to Europe: Inflict MORE PAIN on Google, please
'Platform for piracy' must be punished, or it'll kill us in FIVE YEARS
Phones 4u website DIES as wounded mobe retailer struggles to stay above water
Founder blames 'ruthless network partners' for implosion
Found inside ISIS terror chap's laptop: CELINE DION tunes
REPORT: Stash of terrorist material found in Syria Dell box
Sony says year's losses will be FOUR TIMES DEEPER than thought
Losses of more than $2 BILLION loom over troubled Japanese corp
prev story

Whitepapers

Providing a secure and efficient Helpdesk
A single remote control platform for user support is be key to providing an efficient helpdesk. Retain full control over the way in which screen and keystroke data is transmitted.
WIN a very cool portable ZX Spectrum
Win a one-off portable Spectrum built by legendary hardware hacker Ben Heck
Saudi Petroleum chooses Tegile storage solution
A storage solution that addresses company growth and performance for business-critical applications of caseware archive and search along with other key operational systems.
Protecting users from Firesheep and other Sidejacking attacks with SSL
Discussing the vulnerabilities inherent in Wi-Fi networks, and how using TLS/SSL for your entire site will assure security.
Security for virtualized datacentres
Legacy security solutions are inefficient due to the architectural differences between physical and virtual environments.