Space soldiers save satellite from FLAMING DEATH

The little engine that could rescues $2bn military bird

Choosing a cloud hosting partner with confidence

The US Air Force Space Command's 14-month effort to save a $2bn military communications satellite overcame failed thrusters, threatened explosion, space debris, and destructive radiation, thanks in great measure to tiny thrusters with a mere 0.05 pounds of oomph.

It wasn't easy, as airforce-magazine.com reports in a blow-by-blow account of the rescue published in its January issue, which details for the first time exactly how close the mission came to costly catastrophe.

Space Vehicle-1 was launched on August 10, 2010, with the goal of placing the first satellite of the planned Advanced Extremely High Frequency (AEHF) system into orbit.

The AEHF system, described as having a primary mission of "near-worldwide, secure, survivable satellite communications" among military and civilian leaders and worldwide forces, is a 10X improvement over the current Milstar communications system, the first satellite of which was launched in 1994.

The first AEHF satellite, launched in 2010, was intended to orbit at 22,236 miles above the earth (give or take a hop, step, and a jump), the distance at which a satellite becomes geosynchronous – meaning that one orbit takes exactly as long as one earth day.

SV-1 Atlas launch vehicle

SV-1 aboard Atlas V (credit: United
Launch Alliance – click to enlarge)

Traveling along above the equator – directly overhead the Galápagos Islands, to be exact – the satellite was intended to also be geostationary, meaning that its orbit would keep it above the same spot on earth, rather than wagging back and forth across the equator, which would have been the case had its orbit been at an angle to that mid-earth dividing line.

The launch of the Atlas V carrying SV-1 with its AEHF payload went off without a hitch, placing the 13,420-pound vehicle in its planned highly elliptical orbit, with an apogee of 31,000 miles and a perigee of 143 miles.

It wasn't intended to stay in that unstable orbit for long. The SV-1's propulsion system was scheduled to reduce its apogee and expand its perigee until it reached its eventual geosynchronous, geostationary parking place.

Problems, though, cropped up almost immediately. On August 15, the first firing of the vehicle's main propulsion system, the hydrazine-fueled liquid apogee engine (LAE), failed – the LAE shut down after only a few seconds. The space boffins gave it another go on August 17, with the same result. The LAE also also sent back telemetry that seemed to indicate that it was overheating.

Not good.

According to airforce-magazine.com, the command lead of the Military Satellite Communications Systems Directorate (MILSATCOM) at the Air Force Space Command (AFSPC), Michael Lakos, thought the second shutdown was "an Apollo 13 moment," since the vehicle needed the LAE to achieve its orbital goal. Over at the Space and Missile Systems Center (SMC) in Los Angeles, the head of MILSATCOM, David Madden, thought the mission was lost.

Madden then assembled a brain trust to determine what had gone wrong with the LAE – and fast. They quickly determined that a fuel-line blockage had cripped the engine. More importantly, they advised the vehicle's masters that to try to fire it up again could cause an explosion.

"They probably saved the satellite," Madden told airforce-magazine.com. "We could have had combustion outside of the engine, which could have either totally damaged our payload or caused catastrophic damage to the vehicle."

Another AFSPC boffin was more direct. "We're very, very fortunate that satellite didn't blow up," he said.

Secure remote control for conventional and virtual desktops

More from The Register

next story
GRAV WAVE DRAMA: 'Big Bang echo' may have been grit on the scanner – boffins
Exit Planet Dust on faster-than-light expansion of universe
Mine Bitcoins with PENCIL and PAPER
Forget Sudoku, crunch SHA-256 algos
SpaceX Dragon cargo truck flies 3D printer to ISS: Clawdown in 3, 2...
Craft berths at space station with supplies, experiments, toys
'This BITE MARK is a SMOKING GUN': Boffins probe ancient assault
Tooth embedded in thigh bone may tell who pulled the trigger
DOLPHINS SMELL MAGNETS – did we hear that right, boffins?
Xavier's School for Gifted Magnetotaceans
Big dinosaur wowed females with its ENORMOUS HOOTER
That's right, Doris, I've got biggest snout in the prehistoric world
Japanese volcano eruption reportedly leaves 31 people presumed dead
Hopes fade of finding survivors on Mount Ontake
That glass of water you just drank? It was OLDER than the SUN
One MEELLION years older. Some of it anyway
Canberra drone team dances a samba in Outback Challenge
CSIRO's 'missing bushwalker' found and watered
prev story

Whitepapers

Forging a new future with identity relationship management
Learn about ForgeRock's next generation IRM platform and how it is designed to empower CEOS's and enterprises to engage with consumers.
Storage capacity and performance optimization at Mizuno USA
Mizuno USA turn to Tegile storage technology to solve both their SAN and backup issues.
The next step in data security
With recent increased privacy concerns and computers becoming more powerful, the chance of hackers being able to crack smaller-sized RSA keys increases.
Security for virtualized datacentres
Legacy security solutions are inefficient due to the architectural differences between physical and virtual environments.
A strategic approach to identity relationship management
ForgeRock commissioned Forrester to evaluate companies’ IAM practices and requirements when it comes to customer-facing scenarios versus employee-facing ones.