BT fibre-to-the-premises trial takes 7 hours per install

Fingers, blowers and splitters in Milton Keynes

Top three mobile application threats

Ducts, telegraph poles, manifolds, splitter nodes and a very steady hand

BT said it's taking seven hours on average for two of its engineers to complete one "managed install" of the new kit at a customer's home. The company is trying to push the work down to around four hours, but it hasn't nailed that yet during the trial.

Furthermore, the telco can expect bigger challenges when it begins dealing with much older infrastructure than the relatively well-planned duct system in place in Milton Keynes.

Once a customer signs up for BT's FTTP service, the firm's engineers arrive on-site and proceed to blow fibre through to the punter's home. It's a fiddly task involving lots of spliced fibre that is threaded through to an outside connector, which in turn feeds into a BT-branded box inside the house.

BT splitter node

Splitter node – where the magic happens

The fibre is installed from BT's exchange down to a device called a manifold that resides in the ground or up on telegraph poles. But it's a lengthy process.

Cables containing individual fibres are fed out to a splitter, where engineers then splice it and split it to provide the service to up to 32 customers.

The difficult part for the engineers is in getting the fibre pushed through the tubes via narrow subducts that are already used for existing telecoms infrastructure. BT said that the cabling has to be pulled through by hand as there is no tech in place that could somehow automate the finger-freezing process.

BT kit loaded onto vans for FTTP deployment

To put that into perspective, in the Milton Keynes area alone, BT has distributed 600km of cables and around 4,000 manifolds for the 11,500 homes it has "passed" so far.

Once the cable reaches its destination point, BT engineers then blow the fibre through duct tubes using compressed air. The endgame involves connecting up the splitter to the distribution point, which in turn is plugged into the manifold before finally being threaded through to a customer's property. It's a process known as splicing.

BT air compressed cable

Fibre splicing

An engineer has to strip off the fibre's colour-coded protective coating to get to the delicate, hair-thin piece of cable. It can do nasty things to an engineer if it breaks and gets lodged in their skin.

Once the fibre is exposed, the engineer cleans it with rubbing alcohol and then uses a box excitingly dubbed a "fusion splicer". The device helps to line the cable up and then sticks the two ends together. The ends, guided by the box, have to be lined up accurately, otherwise it flashes a red light confirming that the engineer needs to realign again.

The cable then gets blown into a customer's home and "hey presto" they are given access to BT's fibre network that offers downstream broadband speeds of "up to" 100Mbit/s.

No wonder then that the process is a lengthy one. BT has committed huge man hours to the project, while its main rival Virgin Media says it sees "no compelling reason why" it should heavily invest in FTTP at this time.

For BT, the Milton Keynes trial remains purely a testing ground for now. It is possible that the procedure could change once the company begins rolling out its tech to other regions in the UK. And it's important to note that customers will not be able to choose how fibre is delivered to their home or business. Depending on the infrastructure, they will either get fibre-to-the-premises or fibre-to-the-cabinet.

Beyond that, BT faces local opposition to its OpenReach vans "swamping" streets, estates and businesses as its engineers grapple with all that fibre. It's also getting negative vibes from grumpy landlords too. Ultimately, no matter how exciting the idea of "superfast" broadband might seem, there's a truckload of red tape to cut through first. ®

Combat fraud and increase customer satisfaction

More from The Register

next story
Virgin Media so, so SORRY for turning spam fire-hose on its punters
Hundreds of emails flood inboxes thanks to gaffe
A black box for your SUITCASE: Now your lost luggage can phone home – quite literally
Breakfast in London, lunch in NYC, and your clothes in Peru
AT&T threatens to pull out of FCC wireless auctions over purchase limits
Company wants ability to buy more spectrum space in auction
Turnbull leaves Australia's broadband blackspots in the dark
New Statement of Expectations to NBN Co offers get-out clauses for blackspot builds
Facebook claims 100 MEEELLION active users in India
Who needs China when you've got the next billion in your sights?
Facebook splats in-app chat, whacks brats into crack yakety-yak app
Jibber-jabbering addicts turfed out just as Zuck warned
Google looks to LTE and Wi-Fi to help it lube YouTube tubes
Bandwidth hogger needs tube embiggenment if it's to succeed
prev story

Whitepapers

SANS - Survey on application security programs
In this whitepaper learn about the state of application security programs and practices of 488 surveyed respondents, and discover how mature and effective these programs are.
Combat fraud and increase customer satisfaction
Based on their experience using HP ArcSight Enterprise Security Manager for IT security operations, Finansbank moved to HP ArcSight ESM for fraud management.
The benefits of software based PBX
Why you should break free from your proprietary PBX and how to leverage your existing server hardware.
Top three mobile application threats
Learn about three of the top mobile application security threats facing businesses today and recommendations on how to mitigate the risk.
3 Big data security analytics techniques
Applying these Big Data security analytics techniques can help you make your business safer by detecting attacks early, before significant damage is done.