Render farming is hot!

Server upgrade makes data centre unfit for purpose

Beginner's guide to SSL certificates

I recently revisited my all time favourite consulting experience; the design and construction of a mid-sized render farm. I had never done anything quite like it before; it took a full summer’s worth of research and two months to fully install and test the final design.

The render farm consisted of 400 render nodes, a rack’s worth of storage, a cluster of three Red Hat servers handing out Linux to the render nodes and a single Windows XP system running the controller software. This farm has just finished its fourth year of continuous operation and the client has reluctantly decided that the time has come to replace it.

I had not heard much about this farm since final delivery and the subsequent completion of the first production render. Sitting down with the client and his in-house systems administrator to discuss their trials and tribulations over the past four years working with my “baby” was an eye opener.

Apart from a disk upgrade to the storage rack and a CPU upgrade to the render nodes, very little had been touched on the render farm during it’s operational lifetime. The farm experienced a few disk failures, but nothing above average. The render nodes had grown some bad DIMMs yet had lost but a single motherboard.

Astonishingly, the Linux distribution in use is the same today as on the day it was installed; the configuration files had never once been touched. Considering the evolutionary pace of 3D software I found this hard to believe, but apparently they have gotten along just fine working with a years-old version of Lightwave.

The client had upgraded shortly after the render farm was completed; and this slightly newer version was apparently still compatible with the render farm. Indeed, it was not the speed of the render farm that was driving the request for an upgrade but rather a desire to finally update their software beyond a version nearly four years old. The newer versions of Lightwave will apparently not talk to the vastly dated software on the render farm.

More punch, more power

We went back to my lab, lashed together a few test systems and discovered to our amazement that the entire 400-node render system could probably be replaced with two dozen modern servers running sexy video cards. Numbers were juggled and it was decided that the replacement build would start with a 50-node render farm with two video cards per node.

I asked the client what he would do with the space freed up by such an upgrade. I was worried he would do something silly like packing the datacenter full of storage boxes resulting in compromised airflow. This proved to be a fateful question; apparently this upgrade would free up enough physical space in their datacenter to be able to make a bid on a major contract. Success would mean fleshing their 50 node farm out into a 500-node farm.

It was here that things got gluey. The servers we had just designed easily pulled over three times the power than did the old ones. Their existing datacenter has neither the electrical service nor the cooling to handle anything close to 500 of these new nodes.

The incident serves as an illustration of why a little bit of paranoia is beneficial in the long run. There’s more to upgrades than simply updating software or swapping boxes. Just as we must take into consideration software items such as patches, drivers, and the many and varied ways our systems interact with others, the interaction of our servers with their physical environment is something about which we should always be concerned.

Internet Security Threat Report 2014

More from The Register

next story
The cloud that goes puff: Seagate Central home NAS woes
4TB of home storage is great, until you wake up to a dead device
Azure TITSUP caused by INFINITE LOOP
Fat fingered geo-block kept Aussies in the dark
You think the CLOUD's insecure? It's BETTER than UK.GOV's DATA CENTRES
We don't even know where some of them ARE – Maude
Intel offers ingenious piece of 10TB 3D NAND chippery
The race for next generation flash capacity now on
Want to STUFF Facebook with blatant ADVERTISING? Fine! But you must PAY
Pony up or push off, Zuck tells social marketeers
Oi, Europe! Tell US feds to GTFO of our servers, say Microsoft and pals
By writing a really angry letter about how it's harming our cloud business, ta
SAVE ME, NASA system builder, from my DEAD WORKSTATION
Anal-retentive hardware nerd in paws-on workstation crisis
prev story

Whitepapers

Why and how to choose the right cloud vendor
The benefits of cloud-based storage in your processes. Eliminate onsite, disk-based backup and archiving in favor of cloud-based data protection.
Getting started with customer-focused identity management
Learn why identity is a fundamental requirement to digital growth, and how without it there is no way to identify and engage customers in a meaningful way.
Reg Reader Research: SaaS based Email and Office Productivity Tools
Read this Reg reader report which provides advice and guidance for SMBs towards the use of SaaS based email and Office productivity tools.
The Heartbleed Bug: how to protect your business with Symantec
What happens when the next Heartbleed (or worse) comes along, and what can you do to weather another chapter in an all-too-familiar string of debilitating attacks?
Top 5 reasons to deploy VMware with Tegile
Data demand and the rise of virtualization is challenging IT teams to deliver storage performance, scalability and capacity that can keep up, while maximizing efficiency.