Prendergast sums up the process: "The key was that we had a client that bought into the process and we mitigated against risks small and large by dealing quickly with problems as they arose. My advice to anyone is, the more you do upfront in terms of planning and detailing the complexity of migration, the better."

The must-haves at Sellafield

It is not difficult to imagine the potential risks of a maintenance project at Sellafield, the nuclear processing and former electricity generating site.

Sellafield is operated by Sellafield Ltd, which recently completed a complex project to replace parts of two pipes that are integral to the process of turning nuclear waste (liquor) into glass. The liquor is merged with glass beads and melted, then cooled and placed into tiny welded containers for long-term storage.

A project had been started to replace parts of the piping that transports the glass but had run aground due to problems with the process. At that point Neil Crewdson, head of projects at High Level Waste Plants, took over.

"Worker safety became more of a problem than had been expected"

“I became aware that morale was low because the project team were being blamed for not delivering on an impossible timescale,” he says.

The biggest risk was that the work would continue to disrupt the plant’s core function of reprocessing nuclear waste. The project also risked breaching safety standards by exposing members of the team to excessive levels of radiation.

“I had to argue the case for a six-week delay and then for an increased budget of £3.4m. Both were approved and made all the difference. Now the project team had a timetable that was achievable, albeit with 24-hour working,” says Crewdson.

Crewdson also identified the “must-haves” and “nice-to-haves”. Ninety-five per cent of the latter were reassessed and shelved so the team could work only on what was essential.

The timescale slippage resulted in tension between the operating unit and the project team. Worker safety became more of a problem than had been expected. Radiation levels in the vicinity of the pipe were such that special shielding had to be constructed and the time engineers spent on the site had to be monitored to ensure they did not exceed yearly exposure allowances.

A decisive approach enabled Crewdson and his team to move from a “distress” rating to satisfactory completion. It is an example of how a project which seriously jeopardises the normal work of an organisation can be re-energised through effective risk management.

Footnote: Matthew Prendergast was awarded Project Manager of the Year 2010 at the Association for Project Management Conference in October. Neil Crewdson was awarded Young Project Manager of the year for his work at Sellafield. ®

Build a business case: developing custom apps

More from The Register

next story
KDE releases ice-cream coloured Plasma 5 just in time for summer
Melty but refreshing - popular rival to Mint's Cinnamon's still a work in progress
Leaked Windows Phone 8.1 Update specs tease details of Nokia's next mobes
New screen sizes, dual SIMs, voice over LTE, and more
Mozilla keeps its Beard, hopes anti-gay marriage troubles are now over
Plenty on new CEO's todo list – starting with Firefox's slipping grasp
Apple: We'll unleash OS X Yosemite beta on the MASSES on 24 July
Starting today, regular fanbois will be guinea pigs, it tells Reg
Another day, another Firefox: Version 31 is upon us ALREADY
Web devs, Mozilla really wants you to like this one
Secure microkernel that uses maths to be 'bug free' goes open source
Hacker-repelling, drone-protecting code will soon be yours to tweak as you see fit
Cloudy CoreOS Linux distro declares itself production-ready
Lightweight, container-happy Linux gets first Stable release
prev story

Whitepapers

Implementing global e-invoicing with guaranteed legal certainty
Explaining the role local tax compliance plays in successful supply chain management and e-business and how leading global brands are addressing this.
Boost IT visibility and business value
How building a great service catalog relieves pressure points and demonstrates the value of IT service management.
Why and how to choose the right cloud vendor
The benefits of cloud-based storage in your processes. Eliminate onsite, disk-based backup and archiving in favor of cloud-based data protection.
The Essential Guide to IT Transformation
ServiceNow discusses three IT transformations that can help CIO's automate IT services to transform IT and the enterprise.
Maximize storage efficiency across the enterprise
The HP StoreOnce backup solution offers highly flexible, centrally managed, and highly efficient data protection for any enterprise.