Feeds

A race to the finish

Pert, critical path or crawl to the line?

  • alert
  • submit to reddit

High performance access to file storage

Project management Would you run 145 miles from Birmingham to London non-stop for fun? Of course not, but most years about 80 “ultra” runners do just that. They share the loneliness of the long distance project manager.

These brave souls running the Grand Union Canal Race risk exhaustion and collapse on some lonely stretch of canal but most of them complete the course in times of between 33 and 40 hours. Britain’s longest, and some say toughest, running race is a good analogy for most projects. Entrants discuss at length their game plans – what to eat and drink, how many stops to take, what support to call on, how to cope with stress, and so on. And of course they meet unforeseen circumstances, from getting lost to nipple rash.

The average project manager (PM) can probably relate to the problems of the typical Grand Union Canal Race competitor (if not the rashes). And like these runners, PMs try as hard as possible to build robust plans to reach the objective.

For the past 50 years or so, the question has been what is the best way to model any complex activity – and whether you need specific software to do it.

Though less favoured than in its heyday, Pert (program evaluation and review technique) and the critical path method (CPM) remain cornerstones in project modelling. Pert was invented by a couple of US Navy bigwigs in 1957 to manage nuclear submarine maintenance. Subsequently it was used on huge projects such as the Grenoble Winter Olympics. CPM, developed slightly earlier, is seen as the forerunner to Pert and is sometimes amalgamated within it.

Pert is best known for its network charts, derived from the raw data about all the activities to be undertaken. The chart acts as a metaphor for the flow of time (left to right) and provide an easy visual indication of the dependencies between activities.

Project plan: the stuff in red is the critical path.

Like our canal runners, the PM’s number one obsession when embarking on a project is estimating total duration. How fast can we go?

Pert’s primary deliverable, calculated automatically from the raw data, is the so-called critical path, or the minimum time needed to complete the project, and the listing of linked activities in that minimum path. Once the critical path is calculated, earliest and latest start and finish times for non-critical activities also fall out, and the implications for resourcing and scheduling.

Typically, you number activities or events sequentially (10, 20, 30...), allowing for later additions if needed. An event on the Pert chart is a block, linked to other events in the correct sequence, setting out the order in which events unfold.

The raw data consists of the activity name, and optimistic, pessimistic and expected durations. Different calculation methods may be used to estimate a duration time. Microsoft Project, for example, uses a weighted average from which the critical path is derived.

Once this is done “slack” (or “float”) becomes evident in those activities not on the critical path. Slack is the length of time an activity can be delayed without affecting the critical path.

The Gantt chart displays the critical path, colour-coded. The simplicity of the Gantt chart, and the clarity with which it shows the flow of time, makes it the preferred and primary chart on many projects. Change the data, and the critical path and the Gantt charge change too.

High performance access to file storage

More from The Register

next story
Windows 8.1, which you probably haven't upgraded to yet, ALREADY OBSOLETE
Pre-Update versions of new Windows version will no longer support patches
Android engineer: We DIDN'T copy Apple OR follow Samsung's orders
Veep testifies for Samsung during Apple patent trial
OpenSSL Heartbleed: Bloody nose for open-source bleeding hearts
Bloke behind the cockup says not enough people are helping crucial crypto project
Microsoft lobs pre-release Windows Phone 8.1 at devs who dare
App makers can load it before anyone else, but if they do they're stuck with it
Half of Twitter's 'active users' are SILENT STALKERS
Nearly 50% have NEVER tweeted a word
Windows XP still has 27 per cent market share on its deathbed
Windows 7 making some gains on XP Death Day
Internet-of-stuff startup dumps NoSQL for ... SQL?
NoSQL taste great at first but lacks proper nutrients, says startup cloud whiz
US taxman blows Win XP deadline, must now spend millions on custom support
Gov't IT likened to 'a Model T with a lot of things on top of it'
Microsoft TIER SMEAR changes app prices whether devs ask or not
Some go up, some go down, Redmond goes silent
prev story

Whitepapers

Securing web applications made simple and scalable
In this whitepaper learn how automated security testing can provide a simple and scalable way to protect your web applications.
Five 3D headsets to be won!
We were so impressed by the Durovis Dive headset we’ve asked the company to give some away to Reg readers.
HP ArcSight ESM solution helps Finansbank
Based on their experience using HP ArcSight Enterprise Security Manager for IT security operations, Finansbank moved to HP ArcSight ESM for fraud management.
The benefits of software based PBX
Why you should break free from your proprietary PBX and how to leverage your existing server hardware.
Mobile application security study
Download this report to see the alarming realities regarding the sheer number of applications vulnerable to attack, as well as the most common and easily addressable vulnerability errors.