Feeds

A race to the finish

Pert, critical path or crawl to the line?

  • alert
  • submit to reddit

Secure remote control for conventional and virtual desktops

Project management Would you run 145 miles from Birmingham to London non-stop for fun? Of course not, but most years about 80 “ultra” runners do just that. They share the loneliness of the long distance project manager.

These brave souls running the Grand Union Canal Race risk exhaustion and collapse on some lonely stretch of canal but most of them complete the course in times of between 33 and 40 hours. Britain’s longest, and some say toughest, running race is a good analogy for most projects. Entrants discuss at length their game plans – what to eat and drink, how many stops to take, what support to call on, how to cope with stress, and so on. And of course they meet unforeseen circumstances, from getting lost to nipple rash.

The average project manager (PM) can probably relate to the problems of the typical Grand Union Canal Race competitor (if not the rashes). And like these runners, PMs try as hard as possible to build robust plans to reach the objective.

For the past 50 years or so, the question has been what is the best way to model any complex activity – and whether you need specific software to do it.

Though less favoured than in its heyday, Pert (program evaluation and review technique) and the critical path method (CPM) remain cornerstones in project modelling. Pert was invented by a couple of US Navy bigwigs in 1957 to manage nuclear submarine maintenance. Subsequently it was used on huge projects such as the Grenoble Winter Olympics. CPM, developed slightly earlier, is seen as the forerunner to Pert and is sometimes amalgamated within it.

Pert is best known for its network charts, derived from the raw data about all the activities to be undertaken. The chart acts as a metaphor for the flow of time (left to right) and provide an easy visual indication of the dependencies between activities.

Project plan: the stuff in red is the critical path.

Like our canal runners, the PM’s number one obsession when embarking on a project is estimating total duration. How fast can we go?

Pert’s primary deliverable, calculated automatically from the raw data, is the so-called critical path, or the minimum time needed to complete the project, and the listing of linked activities in that minimum path. Once the critical path is calculated, earliest and latest start and finish times for non-critical activities also fall out, and the implications for resourcing and scheduling.

Typically, you number activities or events sequentially (10, 20, 30...), allowing for later additions if needed. An event on the Pert chart is a block, linked to other events in the correct sequence, setting out the order in which events unfold.

The raw data consists of the activity name, and optimistic, pessimistic and expected durations. Different calculation methods may be used to estimate a duration time. Microsoft Project, for example, uses a weighted average from which the critical path is derived.

Once this is done “slack” (or “float”) becomes evident in those activities not on the critical path. Slack is the length of time an activity can be delayed without affecting the critical path.

The Gantt chart displays the critical path, colour-coded. The simplicity of the Gantt chart, and the clarity with which it shows the flow of time, makes it the preferred and primary chart on many projects. Change the data, and the critical path and the Gantt charge change too.

Secure remote control for conventional and virtual desktops

More from The Register

next story
Microsoft boots 1,500 dodgy apps from the Windows Store
DEVELOPERS! DEVELOPERS! DEVELOPERS! Naughty, misleading developers!
Apple promises to lift Curse of the Drained iPhone 5 Battery
Have you tried turning it off and...? Never mind, here's a replacement
Mozilla's 'Tiles' ads debut in new Firefox nightlies
You can try turning them off and on again
Linux turns 23 and Linus Torvalds celebrates as only he can
No, not with swearing, but by controlling the release cycle
Scratched PC-dispatch patch patched, hatched in batch rematch
Windows security update fixed after triggering blue screens (and screams) of death
prev story

Whitepapers

5 things you didn’t know about cloud backup
IT departments are embracing cloud backup, but there’s a lot you need to know before choosing a service provider. Learn all the critical things you need to know.
Implementing global e-invoicing with guaranteed legal certainty
Explaining the role local tax compliance plays in successful supply chain management and e-business and how leading global brands are addressing this.
Backing up Big Data
Solving backup challenges and “protect everything from everywhere,” as we move into the era of big data management and the adoption of BYOD.
Consolidation: The Foundation for IT Business Transformation
In this whitepaper learn how effective consolidation of IT and business resources can enable multiple, meaningful business benefits.
High Performance for All
While HPC is not new, it has traditionally been seen as a specialist area – is it now geared up to meet more mainstream requirements?