IBM Warwick data centre has a lie down

Zonked by power outage, failed generator, lengthy restart

SaaS data loss: The problem you didn’t know you had

IBM's Warwick, UK, data centre was hit by a power outage on Thursday, causing customers' mission-critical systems to be down for several hours, according to a source.

Many customers use this IBM data centre to host their applications, including Edwards Ltd., a global manufacturer of vacuum pump technologies for precision engineering.

It chose IBM Global Technology Services' Applications on Demand to host its systems at IBM Warwick. Edwards’ SAP applications run under IBM AIX on Power Systems servers, supported by IBM DB2 and an IBM storage area network using a DS8000 array and Tivoli Storage Manager.

IBM states that its Warwick recovery centre is backed by full uninterruptible power supply (UPS) and generators.

According to a source, the power failure occurred at 2.20pm on April 30th and was, unfortunately, followed by a generator failure. This lengthened the outage period, which was then extended by the need to start systems in a regulated sequence. It meant customers with mission-critical systems hosted at the data centre could not use those systems for several hours.

Our source said a Mastercard processor was hit. Its services were back by 19.30, five hours later, but then it was not really prepared for a power outage of this nature.

An IBM spokesperson said: "There was a short interruption to the power supply yesterday, which was quickly resolved. We are working closely with clients to resolve any outstanding issues." ®

Steps to Take Before Choosing a Business Continuity Partner

Latest Comments

Ha!

Me thinkish they did not fill up the tank for the pwer generator.

0
0

Wonder about data center design

I'd like to know if the data center in question was a tier 1, 2, 3, or higher. If built as a tier 1 or 2, I would suspect this type of down-time as redundancy is not a primary issue. However, if designed as a tier 3 or higher, then IBM might need to rethink their build. Of course, putting mission-critical processing into anything but a tier 3+ center is folly to begin with.

0
0

(word correction)

Correction:

"... which also happens a lot with normal ATM debit payments WITHOUT having these disruptions..."

0
0

More from The Register

SCO vs. IBM battle resumes over ownership of Unix
Zombie lawsuit back and wants to suck the brains out of Linux
 breaking news
You don't need phone lines or cable for ANYTHING, says Dish
The satellite-dish man can sort you out with phone and broadband over the air too
 breaking news
What's HP got under wraps? Looks awfully flash and tape shaped
What happens in Vegas won't stay there - we've got the details
AMD lifts the veil on Opteron, ARM chip plans for 2014
Not much action going on in 2013, though
Microsoft borks botnet takedown in Citadel snafu
Stupid Redmond kicked over our honeypots, wail white hats
IBM's $1bn layoffs latest: Now axe swings in US, Canada - reports
Union claims 121 storage bods canned after dismal sales
NetApp musters muscular cluster bluster for ONTAP busters
Storage array OS overhauled to juggle more nodes, go down on you, er, less
HP adds 'Haswell' Xeon E3s to entry ProLiant servers
Gussies up MicroServer for SMBs, adds baby switches