IBM Warwick data centre has a lie down
Zonked by power outage, failed generator, lengthy restart
SaaS data loss: The problem you didn’t know you had
IBM's Warwick, UK, data centre was hit by a power outage on Thursday, causing customers' mission-critical systems to be down for several hours, according to a source.
Many customers use this IBM data centre to host their applications, including Edwards Ltd., a global manufacturer of vacuum pump technologies for precision engineering.
It chose IBM Global Technology Services' Applications on Demand to host its systems at IBM Warwick. Edwards’ SAP applications run under IBM AIX on Power Systems servers, supported by IBM DB2 and an IBM storage area network using a DS8000 array and Tivoli Storage Manager.
IBM states that its Warwick recovery centre is backed by full uninterruptible power supply (UPS) and generators.
According to a source, the power failure occurred at 2.20pm on April 30th and was, unfortunately, followed by a generator failure. This lengthened the outage period, which was then extended by the need to start systems in a regulated sequence. It meant customers with mission-critical systems hosted at the data centre could not use those systems for several hours.
Our source said a Mastercard processor was hit. Its services were back by 19.30, five hours later, but then it was not really prepared for a power outage of this nature.
An IBM spokesperson said: "There was a short interruption to the power supply yesterday, which was quickly resolved. We are working closely with clients to resolve any outstanding issues." ®
COMMENTS
Ha!
Me thinkish they did not fill up the tank for the pwer generator.
Wonder about data center design
I'd like to know if the data center in question was a tier 1, 2, 3, or higher. If built as a tier 1 or 2, I would suspect this type of down-time as redundancy is not a primary issue. However, if designed as a tier 3 or higher, then IBM might need to rethink their build. Of course, putting mission-critical processing into anything but a tier 3+ center is folly to begin with.
(word correction)
Correction:
"... which also happens a lot with normal ATM debit payments WITHOUT having these disruptions..."

IT infrastructure monitoring strategies
Agentless Backup is Not a Myth
Top 10 SIEM implementer’s checklist
Steps to Take Before Choosing a Business Continuity Partner
Enabling efficient data center monitoring