Boeing confirms revised Dreamliner schedule

First delivery late 2008

Secure remote control for conventional and virtual desktops

Boeing has confirmed it will deliver the first 787 Dreamliner in November or December 2008, following a maiden flight early in the year.

The announcement comes a couple of months after the company knocked backed the 787 schedule by six months due to production difficulties. It had previously said it would deliver the first example to All-Nippon Airways by May 2008 following a compressed flight test programme.

Scott Carson, head of Boeing's commercial plane unit, admitted the manufacturer is still "ironing out significant supply chain wrinkles", but promised: "The schedule we revealed in October is unchanged."

To back up its assertion that all is proceeding according to the revised timetable, Boeing yesterday released a nice snap of the 787 production line:

Boeing's 787 production line. Photo: Boeing

The blurb explains: "The Boeing production line is full for the all-new 787 Dreamliner, as work continues on the first flight-test airplane and two airplanes to be used for static and fatigue testing. This photo shows Airplane #1 in the third position, where final structure and systems installations are completed. Behind it, the static-test airplane is in the second position, where it will receive landing gear, engines, and any required interior installations. The fatigue airplane entered final body join 30 Nov."

Boeing currently has 762 orders for the 787, valued at $120bn. ®

Next gen security for virtualised datacentres

More from The Register

next story
Gigantic toothless 'DRAGONS' dominated Earth's early skies
Gummy pterosaurs outlived toothy competitors
Vulture 2 takes a battering in 100km/h test run
Still in one piece, but we're going to need MORE POWER
TRIANGULAR orbits will help Rosetta to get up close with Comet 67P
Probe will be just 10km from Space Duck in October
Boffins ID freakish spine-smothered prehistoric critter: The CLAW gave it away
Bizarre-looking creature actually related to velvet worms
CRR-CRRRK, beep, beep: Mars space truck backs out of slippery sand trap
Curiosity finds new drilling target after course correction
'Leccy racer whacks petrols in Oz race
ELMOFO rakes in two wins in sanctioned race
What does a flashmob of 1,024 robots look like? Just like this
Sorry, Harvard, did you say kilobots or KILLER BOTS?
NASA's rock'n'roll shock: ROLLING STONE FOUND ON MARS
No sign of Ziggy Stardust and his band
Why your mum was WRONG about whiffy tattooed people
They're a future source of RENEWABLE ENERGY
prev story

Whitepapers

5 things you didn’t know about cloud backup
IT departments are embracing cloud backup, but there’s a lot you need to know before choosing a service provider. Learn all the critical things you need to know.
Implementing global e-invoicing with guaranteed legal certainty
Explaining the role local tax compliance plays in successful supply chain management and e-business and how leading global brands are addressing this.
Build a business case: developing custom apps
Learn how to maximize the value of custom applications by accelerating and simplifying their development.
Rethinking backup and recovery in the modern data center
Combining intelligence, operational analytics, and automation to enable efficient, data-driven IT organizations using the HP ABR approach.
Next gen security for virtualised datacentres
Legacy security solutions are inefficient due to the architectural differences between physical and virtual environments.