Boeing confirms revised Dreamliner schedule
First delivery late 2008
Cloud storage: Lower cost and increase uptime
Boeing has confirmed it will deliver the first 787 Dreamliner in November or December 2008, following a maiden flight early in the year.
The announcement comes a couple of months after the company knocked backed the 787 schedule by six months due to production difficulties. It had previously said it would deliver the first example to All-Nippon Airways by May 2008 following a compressed flight test programme.
Scott Carson, head of Boeing's commercial plane unit, admitted the manufacturer is still "ironing out significant supply chain wrinkles", but promised: "The schedule we revealed in October is unchanged."
To back up its assertion that all is proceeding according to the revised timetable, Boeing yesterday released a nice snap of the 787 production line:

The blurb explains: "The Boeing production line is full for the all-new 787 Dreamliner, as work continues on the first flight-test airplane and two airplanes to be used for static and fatigue testing. This photo shows Airplane #1 in the third position, where final structure and systems installations are completed. Behind it, the static-test airplane is in the second position, where it will receive landing gear, engines, and any required interior installations. The fatigue airplane entered final body join 30 Nov."
Boeing currently has 762 orders for the 787, valued at $120bn. ®
COMMENTS
Hence, the name "Dreamliner".....
The original deadline was a dream .
'Course, if it was an Airbus....it would have taken 6 months just to determine when to announce the first production delay.
Ah
Ah brings back memories of all those plastic aeroplanes as they were always hard to assemble out of the box and required much modifications to fit the parts together as one !
Knocked Backed?
I supposed if they were going to deliver early you'd say they "moved forwarded" the schedule, right?
I thought not.

Agentless Backup is Not a Myth
Steps to Take Before Choosing a Business Continuity Partner
Requirements Checklist for Choosing a Cloud Backup and Recovery Service Provider
Cloud storage: Lower cost and increase uptime
SaaS data loss: The problem you didn’t know you had