The government failed to account for the costs of IT when putting together its budget for the 2012 Olympic Games, according to the bean counter watchdogs of the Public Accounts Committee (PAC).

In its 39th report, the PAC said the Olympic Delivery Authority had neglected to include additional costs of £400m, which would cover "IT and site mobilisation and the costs of the CLM Consortium", a project management group appointed by the Olympic Delivery Authority to help it get everything in on time.

This £400m oversight was part of a £900m increase in the total budget for the Olympic Park, announced in 2006. The PAC says the massive underestimate was a result of using the costs of an "urban development corporation" as a benchmark for the running costs of the Olympic Delivery Authority. And they say private sector isn't leaner than public.

The report also found the authority has "seriously overestimated" the amount of private sector funding it was likely to receive. Planners budgeted for £738m of private sector funding, but it turned out that there was not enough time to negotiate the necessary contracts, so the money is unlikely to materialise.

The games were originally expected to cost around £2bn. That figure has since risen to £9bn. And although they managed a £400m tech-related oversight, at least planners managed to get the London Olympic logo in on time and looking just fabulous. ®

Security for virtualized datacentres

More from The Register

next story
It's Big, it's Blue... it's simply FABLESS! IBM's chip-free future
Or why the reversal of globalisation ain't gonna 'appen
'Hmm, why CAN'T I run a water pipe through that rack of media servers?'
Leaving Las Vegas for Armenia kludging and Dubai dune bashing
Bitcasa bins $10-a-month Infinite storage offer
Firm cites 'low demand' plus 'abusers'
Facebook slurps 'paste sites' for STOLEN passwords, sprinkles on hash and salt
Zuck's ad empire DOESN'T see details in plain text. Phew!
CAGE MATCH: Microsoft, Dell open co-located bit barns in Oz
Whole new species of XaaS spawning in the antipodes
Microsoft and Dell’s cloud in a box: Instant Azure for the data centre
A less painful way to run Microsoft’s private cloud
AWS pulls desktop-as-a-service from the PC
Support for PCoIP protocol means zero clients can run cloudy desktops
prev story

Whitepapers

Why cloud backup?
Combining the latest advancements in disk-based backup with secure, integrated, cloud technologies offer organizations fast and assured recovery of their critical enterprise data.
A strategic approach to identity relationship management
ForgeRock commissioned Forrester to evaluate companies’ IAM practices and requirements when it comes to customer-facing scenarios versus employee-facing ones.
Security for virtualized datacentres
Legacy security solutions are inefficient due to the architectural differences between physical and virtual environments.
Reg Reader Research: SaaS based Email and Office Productivity Tools
Read this Reg reader report which provides advice and guidance for SMBs towards the use of SaaS based email and Office productivity tools.
New hybrid storage solutions
Tackling data challenges through emerging hybrid storage solutions that enable optimum database performance whilst managing costs and increasingly large data stores.