The £6.2bn National Programme for IT will henceforward be known as the £12.4bn National Programme for IT, after a long-awaited National Audit Office report into the ambitious NHS IT scheme revealed the full extent of its costs to date.

But the Department of Health always knew it was going to cost as much as £12.5bn, it said today, even in those days when it said the programme was going to cost half as much.

Moreover, it insisted today, that the doubled price tag did not mean that the Programme has gone over-budget.

Speaking at the launch of the NAO report this morning, Chris Shapcott, director of health value for money studies, said there were "appraisals" done by the Department of Health "prior to the contracts being let" to the major suppliers in 2003.

These were documented and accounted for the £12.4bn cost of the programme that the Department's IT body, Connecting for Health, has now been forced to admit by the publication of the NAO report.

"They always recognised there would be more spending," he said.

Health minister Lord Warner said that the Programme, "despite what some people say, is on budget."

"The NAO has confirmed the cost has not overrun," he said. And anyway, the costs were not important.

"We need to talk more about the benefits. In the long term this project will pay for itself," he added.

The vastly inadequate cost estimates touted by Connecting for Health since the inception of the programme (once £2.3bn) have been ridiculed by independent scrutiny before. It had forced the Programme to admit that its £6.2bn cost estimate did not include the cost of implementing the systems, only developing them.

The same story was given again today by Richard Granger, boss of Connecting for Health, with some elaboration. It is normal in the IT industry, he claimed, for people to disregard the cost of implementing a system when estimating its price. It must be a little like budgeting for the cost of a new house, but only accounting for the land and materials - the cost of the builders is irrelevant, apparently.®

Secure remote control for conventional and virtual desktops

More from The Register

next story
Found inside ISIS terror chap's laptop: CELINE DION tunes
REPORT: Stash of terrorist material found in Syria Dell box
Show us your Five-Eyes SECRETS says Privacy International
Refusal to disclose GCHQ canteen menus and prices triggers Euro Human Rights Court action
Radio hams can encrypt, in emergencies, says Ofcom
Consultation promises new spectrum and hints at relaxed licence conditions
Snowden, Dotcom, throw bombs into NZ election campaign
Claim of tapped undersea cable refuted by Kiwi PM as Kim claims extradition plot
Heavy VPN users are probably pirates, says BBC
And ISPs should nab 'em on our behalf
Former Bitcoin Foundation chair pleads guilty to money-laundering charge
Charlie Shrem plea deal could still get him five YEARS in chokey
prev story

Whitepapers

Secure remote control for conventional and virtual desktops
Balancing user privacy and privileged access, in accordance with compliance frameworks and legislation. Evaluating any potential remote control choice.
Saudi Petroleum chooses Tegile storage solution
A storage solution that addresses company growth and performance for business-critical applications of caseware archive and search along with other key operational systems.
High Performance for All
While HPC is not new, it has traditionally been seen as a specialist area – is it now geared up to meet more mainstream requirements?
Security for virtualized datacentres
Legacy security solutions are inefficient due to the architectural differences between physical and virtual environments.
Providing a secure and efficient Helpdesk
A single remote control platform for user support is be key to providing an efficient helpdesk. Retain full control over the way in which screen and keystroke data is transmitted.