Bradford procurement slammed

Audit Commission blasts 'weak' process

  • alert
  • submit to reddit

Choosing a cloud hosting partner with confidence

Bradford Metropolitan District Council has been criticised for the way it mismanaged the procurement of a key Asset Management Project (AMP).

Local authority watchdog the Audit Commission has published a damning report highlighting weaknesses in the way the authority sought to find a partner to manage its assets portfolio, a contract that is worth an estimated £1.2bn over 20 years.

The commission launched an inquiry last year after it received allegations from anonymous sources over the way the procurement process was being handled.

Reporting back, the district auditor Ivan McConnell said because of its complexity and lack of unanimous political support within the council, "progress on the project has not always been smooth".

As a result, he found the overall management of the project fell short of the "high standards expected generally for local authorities".

He noted that: "More formal arrangements would have helped to assure members that the portfolio of projects was being managed effectively to maximise benefits and minimise risks."

Because of its poor management, the scheme ended up without a fully effective project structure, the auditor said.

He found there was no dedicated project team, internal resources supporting the project were "at times stretched beyond their capacity" and there were "no formally documented roles and responsibilities for team members". Bradford failed to document the project properly, meaning the records are incomplete. In addition, it failed to predict the fees it eventually paid out to financial advisers on the project, meaning it probably broke its own and European procurement rules.

"In my view these deficiencies contributed to delays in progress and meant that key project control tasks such as management of advisers and documentation were not effectively completed."

He said the council needed to re-appraise its position on the AMP "quickly" and ensure any future project structure for the procurement of asset management is strengthened.

"This report is not about the decision taken by the council to improve its asset management but about the inability of council officers to employ effective procedures to manage this critical project. My conclusion is that there have been significant weaknesses in the appropriate standards required to manage a complex project of this kind."

However, he added that the council's interim chief executive has accepted the recommendations of the report without reservation and has already taken action to implement the report's recommendations.

Read the report here (PDF: 126KB).

Copyright © eGov monitor Weekly

eGov monitor Weekly is a free e-newsletter covering developments in UK eGovernment and public sector IT over the last seven days. To register go here.

Intelligent flash storage arrays

More from The Register

next story
WHY did Sunday Mirror stoop to slurping selfies for smut sting?
Tabloid splashes, MP resigns - but there's a BIG copyright issue here
Spies, avert eyes! Tim Berners-Lee demands a UK digital bill of rights
Lobbies tetchy MPs 'to end indiscriminate online surveillance'
Scrapping the Human Rights Act: What about privacy and freedom of expression?
Justice minister's attack to destroy ability to challenge state
Inequality increasing? BOLLOCKS! You heard me: 'Screw the 1%'
There's morality and then there's economics ...
Google hits back at 'Dear Rupert' over search dominance claims
Choc Factory sniffs: 'We're not pirate-lovers - also, you publish The Sun'
EU to accuse Ireland of giving Apple an overly peachy tax deal – report
Probe expected to say single-digit rate was unlawful
While you queued for an iPhone 6, Apple's Cook sold shares worth $35m
Right before the stock took a 3.8% dive amid bent and broken mobe drama
prev story

Whitepapers

A strategic approach to identity relationship management
ForgeRock commissioned Forrester to evaluate companies’ IAM practices and requirements when it comes to customer-facing scenarios versus employee-facing ones.
Storage capacity and performance optimization at Mizuno USA
Mizuno USA turn to Tegile storage technology to solve both their SAN and backup issues.
High Performance for All
While HPC is not new, it has traditionally been seen as a specialist area – is it now geared up to meet more mainstream requirements?
Beginner's guide to SSL certificates
De-mystify the technology involved and give you the information you need to make the best decision when considering your online security options.
Security for virtualized datacentres
Legacy security solutions are inefficient due to the architectural differences between physical and virtual environments.