NPfIT boss prepares to cut failing suppliers

And renames the whole shebang for good measure

  • alert
  • submit to reddit

Key suppliers in the NHS' £6.2bn IT project are to be replaced because they are not delivering, according to Richard Granger, director general of the National Programme for IT (NPfIT). Granger would not say which companies are failing, but confirmed that none of the four main local service providers - BT, Accenture, CSC and Fujitsu - is in the danger zone.

Contracts are set up so that no one is paid until work is done, but in those areas still behind schedule, Granger is prepared to cut non-performing contractors, the Financial Times reports: "If suppliers cannot do the job, they will be replaced. Some of that will occur over the next few months."

He went on to acknowledge that progress on the ten-year project has been, and will continue to be, difficult. He recognised that the project had suffered delays, but told delegates at the Healthcare Computing Conference in Harrogate that "substantial progress" has been made: kit is beginning to be installed, and pilot projects have been returning encouraging results.

But he hit out at detractors, accusing them of looking for failure, and saying that a "dip" in the project was only to be expected.

"We have this national sickness about what the French call grands projects," he said. "When it goes into an entirely predictable dip, and when it has to deal with a lot of real problems, we get this attack on the programme."

Granger could be accused of being slightly disingenuous here. The NPfIT has always been a highly controversial project, and has been opposed by many people in the medical profession since its earliest days. Project managers have also been criticised for failing to consult sufficiently with GPs, many of whom oppose core elements of the project, saying patient data could be at risk.

In January this year, the National Audit Office warned that if low levels of GP support were not addressed, the project was in danger of missing its deadlines. The British Medical Association has also warned its members to avoid trialling the flagship Choose and Book referrals service, also over fears that it could compromise patient confidentiality.

Finally, in the best tradition of projects in trouble, the NPfIT is being renamed and will now be known as Connecting for Health. ®

Related stories

GPs have no faith in £6bn NHS IT programme
Flagship NHS project in danger
NPfIT must win medical hearts and minds

More from The Register

next story
Phones 4u slips into administration after EE cuts ties with Brit mobe retailer
More than 5,500 jobs could be axed if rescue mission fails
Israeli spies rebel over mass-snooping on innocent Palestinians
'Disciplinary treatment will be sharp and clear' vow spy-chiefs
Apple CEO Tim Cook: TV is TERRIBLE and stuck in the 1970s
The iKing thinks telly is far too fiddly and ugly – basically, iTunes
Huawei ditches new Windows Phone mobe plans, blames poor sales
Giganto mobe firm slams door shut on Microsoft. OH DEAR
Phones 4u website DIES as wounded mobe retailer struggles to stay above water
Founder blames 'ruthless network partners' for implosion
Found inside ISIS terror chap's laptop: CELINE DION tunes
REPORT: Stash of terrorist material found in Syria Dell box
Show us your Five-Eyes SECRETS says Privacy International
Refusal to disclose GCHQ canteen menus and prices triggers Euro Human Rights Court action
prev story

Whitepapers

Secure remote control for conventional and virtual desktops
Balancing user privacy and privileged access, in accordance with compliance frameworks and legislation. Evaluating any potential remote control choice.
Saudi Petroleum chooses Tegile storage solution
A storage solution that addresses company growth and performance for business-critical applications of caseware archive and search along with other key operational systems.
High Performance for All
While HPC is not new, it has traditionally been seen as a specialist area – is it now geared up to meet more mainstream requirements?
Security for virtualized datacentres
Legacy security solutions are inefficient due to the architectural differences between physical and virtual environments.
Providing a secure and efficient Helpdesk
A single remote control platform for user support is be key to providing an efficient helpdesk. Retain full control over the way in which screen and keystroke data is transmitted.